Transforming the core and face of construction…

Car Parks Works

Start Date: April 2023

Duration: 4 Weeks

Acciona Car Park Works

Description of Works:

We were appointed by the principal contractor of the North London Heat and Power Project to carry out works in the welfare compound car park.

The works involved the installation of handrails and timber railings segregating parking spaces, to improve pedestrian, vehicle segregation in the welfare compound.

The work involved installation of approximately 200 linear meters of railing. Due to the presence of numerous underground services all work was carried out under a permit to dig and installation of the railings was a mix of concreted posts and posts secured to hard standing using post shoes where the presence of underground services was confirmed.